The CNI Process

CNI fundamentally recognises the strength and value of community led action and taking a place-based approach to deliver deep and lasting change. The project supports and enables the 6 CNI islands to organise, plan, and deliver their own solutions most suited to the local community, resources and environment. The experience of Community Energy Scotland and its member organisations informs the process and methodology throughout the project, with emphasis on enabling community change and resilience at a local level. This process reflects an adaptable series of actions, which can be changed to suit specific community needs. Above all, it is essential that the process ensures that planning and action are co-created with the community, to prioritise actions that will have the most impact.

Once the six CNI islands were identified by the Scottish Government Islands Team, Community Energy Scotland was brought in as the project delivery partner based on their experience of delivering decarbonisation while working with island communities.  

Community Led Approach

For the project to be beneficial and respected, it was important that each island community took the lead in making decisions about how the project developed, to reflect the different island contexts and utilise local knowledge.  

Steering Groups

The project structure reflected this understanding of the need to put the community at the centre of the process and each island set up a Steering Group consisting of a range of community representatives. The Steering Group’s role is to represent the wider community and is responsible for supporting the Anchor Organisation and Community Development Officer (CDO) in planning and delivering the project.  

Local Anchor Organisations

The Steering Group identified a Local Anchor Organisation to receive project funding to employ a CNI CDO. The Anchor Organisation was already working with the island community and so had a network of trusted relationships, local knowledge and expertise, and experience of delivering community projects.

Community Development Officers

The CDOs’ role is vital as they are the direct link between all the project partners and the island community (see figure below indicating the relationships of support between the different partners in the project). When working with external partners, stakeholders, and technical experts, clear communication is important to ensure local knowledge and expertise is recognised and valued.

Community Energy Scotland (CES)

CES’s role is to support the islands in delivering the project by working closely with CDOs and Anchor Organisations and wider island communities. They also provide technical input and report back to the Scottish Government Islands Team on project progress.

As overall project leaders the Scottish Government Islands Team meet regularly with CES, CDOs and other project partners – providing support as well as funding.   

The CNI Project Group

Communication across the project partners is important to ensure knowledge sharing and mutual support. The CNI Project Group, consisting of CDOs, Anchor Organisation/Steering Group representatives, CES, members of the Scottish Government Islands Team, meet fortnightly for project updates and discussions. 

CNI Values

To help create a sense of shared ownership of the project and try to capture good practice in communication and project processes, a CNI Project Guide was created. This document was co-written by the CNI Project Group and scribed by CES and is intended to act as a living document, capturing all aspects of the project. 

The starting point of the Project Guide was to agree a set of shared Project Group Values which reflect the collective approach to CNI: 

Project Timeline

Carbon Audits

November 2022 to February 2023

Community engagement and priority setting

November 2022 to March 2023 

Community Climate Actions Plans

Complete May 2023

Investment plans​ and funding

2024